NEW QUESTION 46
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?

  • A. Top-down
  • B. Strict bottom-up
  • C. Bottom-up
  • D. Free planning

Answer: C

 

NEW QUESTION 47
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

  • A. A delivery document type must be configured.
  • B. A sold to party is necessary.
  • C. A shipping point is necessary.
  • D. A sales order must be created in advance.

Answer: B,C

 

NEW QUESTION 48
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Planned revenue can be transferred from a sales quotation.
  • B. Planned revenue requires a sales order assigned to a WBS element.
  • C. Actual revenue is posted via a billing plan assigned to a WBS element.
  • D. Actual revenue is posted via a billing document created from a sales order

Answer: A,D

 

NEW QUESTION 49
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The Project Stock indicator is set in the project definition (non-valuated or valuated).
  • B. The network is assigned to a sales order item.
  • C. The material master of the component must permit project stock management.
  • D. The network activity is assigned to a WBS element.
  • E. A procurement indicator must be assigned to the activity.

Answer: A,C,E

 

NEW QUESTION 50
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

  • A. The person responsible for the work center
  • B. The person responsible for the network activity
  • C. The person responsible for the superior WBS element
  • D. The MRP controller for the network

Answer: D

 

NEW QUESTION 51
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. Subnetworks must be scheduled separately from the superior network.
  • B. Maintenance orders can be defined as subnetworks.
  • C. The scheduling type of a subnetwork is always copied from the superior network.
  • D. A subnetwork cannot be defined for a superior subnetwork.

Answer: B

 

NEW QUESTION 52
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

  • A. Cost element report on budget updates
  • B. Structure overview for budgets
  • C. Hierarchical report on budget updates
  • D. Line item report for budgets

Answer: D

 

NEW QUESTION 53
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Project simulations can create purchase requisitions.
  • B. Multiple project simulations can be used simultaneously.
  • C. Project simulations can be used to plan structures and costs.
  • D. Project simulations allow posting of actual data.
  • E. Project simulations can be created without using an operational project as a template.

Answer: B,C,E

 

NEW QUESTION 54
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the network activity
  • B. Forecast dates of the WBS
  • C. Basic dates of the WBS
  • D. Actual dates of the network activity

Answer: A

 

NEW QUESTION 55
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Cost element reports
  • B. Hierarchical reports
  • C. Resource reports
  • D. Structure information system reports

Answer: D

 

NEW QUESTION 56
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Document information records
  • B. Basic dates for activities
  • C. Relationships
  • D. Internally processed activities
  • E. Material components

Answer: C,D,E

 

NEW QUESTION 57
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.

  • A. The factory calendar in the work center used for the internal processing activity
  • B. The relationships between activity elements
  • C. An activated Scheduling indicator in the control key of the internal processing activity
  • D. Whether the work for the internal activity is greater than its duration
  • E. The unit (for example, hour, day) of the field Normal Duration field of the activity

Answer: A,B,C

 

NEW QUESTION 58
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  • B. The duration is missing in the activity.
  • C. The formula for costing in the work center is incorrect.
  • D. The Determine Costs indicator in the network header rules out planned cost calculation.
  • E. Integrated planning for the network is active.

Answer: A,B,D

 

NEW QUESTION 59
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Project profile
  • B. Network profile
  • C. Parameters for the network type
  • D. Network type

Answer: C

 

NEW QUESTION 60
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.

  • A. Capacity requirements
  • B. Project-relevant purchase orders
  • C. Maintenance orders assigned to an activity
  • D. Production orders assigned to WBS elements

Answer: A,C

 

NEW QUESTION 61
How can you update the degree of processing for an activity?

  • A. By scheduling the activity
  • B. By changing the activity
  • C. By confirming the activity
  • D. By using results analysis

Answer: C

 

NEW QUESTION 62
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions are mandatory for Milestone Trend Analysis (MTA).
  • B. Project versions can be changed.
  • C. Project versions can be created automatically based on user status.
  • D. Manually created project versions always require a project version profile.

Answer: A,B

 

NEW QUESTION 63
......