
Free SAP C-TS412-1909 Test Practice Test Questions Exam Dumps
Prepare Top SAP C-TS412-1909 Exam Audio Study Guide Practice Questions Edition
NEW QUESTION 46
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Strict bottom-up
- C. Bottom-up
- D. Free planning
Answer: C
NEW QUESTION 47
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A delivery document type must be configured.
- B. A sold to party is necessary.
- C. A shipping point is necessary.
- D. A sales order must be created in advance.
Answer: B,C
NEW QUESTION 48
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue can be transferred from a sales quotation.
- B. Planned revenue requires a sales order assigned to a WBS element.
- C. Actual revenue is posted via a billing plan assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: A,D
NEW QUESTION 49
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- B. The network is assigned to a sales order item.
- C. The material master of the component must permit project stock management.
- D. The network activity is assigned to a WBS element.
- E. A procurement indicator must be assigned to the activity.
Answer: A,C,E
NEW QUESTION 50
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The person responsible for the work center
- B. The person responsible for the network activity
- C. The person responsible for the superior WBS element
- D. The MRP controller for the network
Answer: D
NEW QUESTION 51
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. Subnetworks must be scheduled separately from the superior network.
- B. Maintenance orders can be defined as subnetworks.
- C. The scheduling type of a subnetwork is always copied from the superior network.
- D. A subnetwork cannot be defined for a superior subnetwork.
Answer: B
NEW QUESTION 52
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Structure overview for budgets
- C. Hierarchical report on budget updates
- D. Line item report for budgets
Answer: D
NEW QUESTION 53
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Project simulations can create purchase requisitions.
- B. Multiple project simulations can be used simultaneously.
- C. Project simulations can be used to plan structures and costs.
- D. Project simulations allow posting of actual data.
- E. Project simulations can be created without using an operational project as a template.
Answer: B,C,E
NEW QUESTION 54
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
- A. Basic dates of the network activity
- B. Forecast dates of the WBS
- C. Basic dates of the WBS
- D. Actual dates of the network activity
Answer: A
NEW QUESTION 55
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Cost element reports
- B. Hierarchical reports
- C. Resource reports
- D. Structure information system reports
Answer: D
NEW QUESTION 56
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.
- A. Document information records
- B. Basic dates for activities
- C. Relationships
- D. Internally processed activities
- E. Material components
Answer: C,D,E
NEW QUESTION 57
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. The factory calendar in the work center used for the internal processing activity
- B. The relationships between activity elements
- C. An activated Scheduling indicator in the control key of the internal processing activity
- D. Whether the work for the internal activity is greater than its duration
- E. The unit (for example, hour, day) of the field Normal Duration field of the activity
Answer: A,B,C
NEW QUESTION 58
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.
- A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
- B. The duration is missing in the activity.
- C. The formula for costing in the work center is incorrect.
- D. The Determine Costs indicator in the network header rules out planned cost calculation.
- E. Integrated planning for the network is active.
Answer: A,B,D
NEW QUESTION 59
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Project profile
- B. Network profile
- C. Parameters for the network type
- D. Network type
Answer: C
NEW QUESTION 60
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Capacity requirements
- B. Project-relevant purchase orders
- C. Maintenance orders assigned to an activity
- D. Production orders assigned to WBS elements
Answer: A,C
NEW QUESTION 61
How can you update the degree of processing for an activity?
- A. By scheduling the activity
- B. By changing the activity
- C. By confirming the activity
- D. By using results analysis
Answer: C
NEW QUESTION 62
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions are mandatory for Milestone Trend Analysis (MTA).
- B. Project versions can be changed.
- C. Project versions can be created automatically based on user status.
- D. Manually created project versions always require a project version profile.
Answer: A,B
NEW QUESTION 63
......
Go to C-TS412-1909 Questions - Try C-TS412-1909 dumps pdf : https://torrentvce.pass4guide.com/C-TS412-1909-dumps-questions.html